Energy Center Shift Duties 1900hrs-0700hrs Cori

Plant rounds and readings in the Energy Center. Warmed #3 Boiler, Blew down  #1 Boiler and checked LWCO. Tested boiler water and cooling towers water.  Med gas Manifold readings. Metasys Checks and Cold and/or warm calls.

Added 2.5 gal of halochlor to Yard Tower.

Changed Thermostat in room 462.

worked on P.M.’s.

Metasys Alarm for SJMH Primary Bulk  Nitrogen Liquid Low.